The City of Morden will be installing a storm sewer and filling the ditch on the south side of S Railway St from Mountain St to 9th St. This project will improve traffic safety and resolve currently existing maintenance issues related to the ditch profile.

The City’s noise by-law limits construction work hours to between 6:00 a.m. and 11:00 p.m. from Monday to Saturday, and 10:00 a.m. to 11:00 p.m. on Sundays; we do not expect to be working outside of these hours.

Please stay a safe distance from the working area, and be vigilant for moving vehicles and equipment. To report any unsafe activity at the site, please contact the Project Manager.


Schedule of construction beginning July 10, 2019
, and tentatively finished by the end of July 30, 2019.

One lane closure is expected for this section of S Railway St but the full closure is possible to ensure traffic and pedestrian safety. Access for local traffic will be maintained at all times.

Contractor Project Manager  
Bernie’s Backhoe Service
Bernie Giesbrecht
204-822-4825
Tatiana Sinchenko
Engineering Assistant
204-822-4434