The City of Morden will be installing storm sewer at N Railway backlane/7th St intersection and across N Railway St and reconstructing sidewalks and curbing on the east side of 7th St from back lane to N Railway St. The project will improve drainage in this challenging area, as well as accessibility and safety for all active transportation users.

The City’s noise by-law limits construction work hours to between 6:00 a.m. and 11:00 p.m. from Monday to Saturday, and 10:00 a.m. to 11:00 p.m. on Sundays; we do not expect to be working outside of these hours.

Please stay a safe distance from the working area, and be vigilant for moving vehicles and equipment. To report any unsafe activity at the site, please contact the Project Manager.

Schedule of construction beginning July 4, 2019, and tentatively finished by the end of August 20, 2019.

7th St from N railway back lane to N Railway St and N Railway St from 7th St to 6th St will be closed on and off during construction period when construction crews are on site. Parking will be restricted in the area. Please watch for the signs and barricades. Pedestrian access to Legion will be maintained at all times.

Concrete works Contractor Storm Sewer Works Contractor Project Manager  
Schulz Concrete
Ed Schulz
204-823-0892
Horizon Earthworks
Allan Jones
204-384-1103
Tatiana Sinchenko
Engineering Assistant
204-822-4434